### Objectives
|
||||
|
||||
* Allow users to add contacts remotely, as well as by meeting in person
|
||||
* Support features that are common in other messaging apps: image attachments, a PIN lock, and a dark UI theme
|
||||
* Make it easier for organizations such as OCCRP to integrate Briar blogs and messages into their publishing workflows
|
||||
* Reduce power consumption
|
||||
* Support the use of Tor bridges in countries such as China where access to Tor is blocked
|
||||
* Establish a reproducible build process so users can be sure the app they are using was built from the published source code
|
||||
|
||||
### Deliverables
|
||||
|
||||
1. Adding contacts remotely
|
||||
* Protocol and UX for adding contacts remotely via Tor, extensible to other transports
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
2. Image attachments
|
||||
* Update sync protocol to support syncing large messages
|
||||
* Update database and sync API to support storing and retrieving large messages
|
||||
* Update all existing sync clients to use new database and sync API
|
||||
* UX for sending and displaying image attachments
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
3. Account sign in improvements
|
||||
* Remind user to sign in after device is restarted
|
||||
* Optional PIN lock feature, enabling app to be locked while remaining signed in
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
4. Dark theme
|
||||
* Dark UI theme, easier to use in low light
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
5. Headless server/desktop app
|
||||
* Enable OCCRP to publish Briar messages and blogs from their existing tools
|
||||
* Refactor Tor plugin to remove Android dependencies
|
||||
* Implement background service
|
||||
* Implement basic CLI for adding contacts, sending private messages and blog posts
|
||||
* User testing
|
||||
|
||||
6. Power management improvements
|
||||
* Detect and mitigate power management features affecting background services
|
||||
* UX for adding Briar to whitelists where required to maintain background connectivity
|
||||
* Option to disable background connectivity when running on battery power
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
7. Research how to reduce battery impact of Tor hidden services
|
||||
* Research and document Tor’s behaviour in all Android power management states
|
||||
* Identify changes to allow device to spend more time asleep without impacting hidden service availability
|
||||
* Work with Tor developers to ensure proposed changes do not impact anonymity
|
||||
|
||||
8. Tor bridges
|
||||
* Support for Tor bridges based on Guardian project’s work
|
||||
* Use OONI data to create list of locations where bridges should be used
|
||||
* Include fresh bridge and location lists in each release
|
||||
* Automatically enable bridges when current location requires them
|
||||
* UX to enable bridges manually if needed
|
||||
* User testing
|
||||
* Update user manual
|
||||
|
||||
9. Reproducible builds
|
||||
* Entire app, including Tor binaries, to be built reproducibly from source
|
||||
* Document build process
|
||||
|
||||
### Personnel
|
||||
|
||||
The team will consist of six people: the project lead, two developers, a user experience designer, a usability expert, and a technical writer.
|
||||
|
||||
1. Adding contacts remotely
|
||||
* Project lead: 25 days
|
||||
* Developer: 20 days
|
||||
* Designer: 5 days
|
||||
* Usability: 2 days
|
||||
* Writer: 1 day
|
||||
* Total: 53 days
|
||||
|
||||
2. Image attachments
|
||||
* Project lead: 50 days
|
||||
* Developer: 65 days
|
||||
* Designer: 5 days
|
||||
* Usability: 2 days
|
||||
* Writer: 1 day
|
||||
* Total: 123 days
|
||||
|
||||
3. Account sign-in improvements
|
||||
* Project lead: 5 days
|
||||
* Developer: 6 days
|
||||
* Designer: 6 days
|
||||
* Usability: 2 days
|
||||
* Writer: 1 day
|
||||
* Total: 20 days
|
||||
|
||||
4. Dark theme
|
||||
* Developer: 5 days
|
||||
* Designer: 5 days
|
||||
* Usability: 1 day
|
||||
* Writer: 1 day
|
||||
* Total: 12 days
|
||||
|
||||
5. Headless desktop/server app
|
||||
* Developer: 20 days
|
||||
* Usability: 2 days
|
||||
* Total: 22 days
|
||||
|
||||
6. Power management improvements
|
||||
* Project lead: 15 days
|
||||
* Developer: 20 days
|
||||
* Designer: 6 days
|
||||
* Usability: 2 days
|
||||
* Writer: 1 day
|
||||
* Total: 44 days
|
||||
|
||||
7. Research how to reduce battery impact of Tor hidden services
|
||||
* Project lead: 30 days
|
||||
* Developer: 30 days
|
||||
* Total: 60 days
|
||||
|
||||
8. Tor bridges
|
||||
* Developer: 25 days
|
||||
* Designer: 5 days
|
||||
* Usability: 2 days
|
||||
* Writer: 2 days
|
||||
* Total: 34 days
|
||||
|
||||
9. Reproducible builds
|
||||
* Developer: 20 days
|
||||
* Total: 20 days
|
||||